Tunnel construction, a critical aspect of railway engineering, is a repetitive process with distinct linear characteristics. While the Linear Scheduling Method (LSM) is widely used for scheduling optimization in linear projects, it struggles to accommodate dynamic construction sequences, reverse construction, and flexible team allocation. Minimizing the project duration is a primary objective in tunnel construction scheduling optimization. To optimize tunnel construction, we propose a duration-shortening method using additional working surfaces, adaptable to multi-segment and multi-team scenarios. A dynamic optimization model is developed for tunnel construction scheduling, integrating LSM, soft logic, Work Breakdown Structure (WBS), and Resource Breakdown Structure (RBS) within a dynamic scheduling framework. This model analyzes logical relationships, work continuity, temporal and spatial constraints, and resource variation, focusing on reverse construction. The Mixed-Integer Programming (MIP) approach is used to build the mathematical model, solved with both exact algorithms and Genetic Algorithms (GA), and implemented in Python 3.12.7. Both algorithms perform well, with the GA excelling at handling complex constraints. Case studies confirm the method’s effectiveness in optimizing durations, devising flexible schedules, and improving efficiency and practicality. This research provides both theoretical insights and practical guidance for tunnel construction scheduling optimization in railway engineering.

Details

1009240
Business indexing term
Title
Dynamic Optimization of Tunnel Construction Scheduling in a Reverse Construction Scenario
Author
Wei, Jianying 1   VIAFID ORCID Logo  ; Liu, Yuming 1 ; Lu, Xiaochun 1   VIAFID ORCID Logo  ; Zhao, Rong 2 ; Wang, Gan 1 

 School of Economics and Management, Beijing Jiaotong University, Beijing 100044, China; [email protected] (J.W.); [email protected] (X.L.); [email protected] (G.W.) 
 China Academy of Building Research, Beijing 100013, China; [email protected] 
Publication title
Systems; Basel
Volume
13
Issue
3
First page
168
Publication year
2025
Publication date
2025
Publisher
MDPI AG
Place of publication
Basel
Country of publication
Switzerland
Publication subject
e-ISSN
20798954
Source type
Scholarly Journal
Language of publication
English
Document type
Journal Article
Publication history
 
 
Online publication date
2025-02-27
Milestone dates
2025-01-20 (Received); 2025-02-25 (Accepted)
Publication history
 
 
   First posting date
27 Feb 2025
ProQuest document ID
3182195201
Document URL
https://www.proquest.com/scholarly-journals/dynamic-optimization-tunnel-construction/docview/3182195201/se-2?accountid=208611
Copyright
© 2025 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/). Notwithstanding the ProQuest Terms and Conditions, you may use this content in accordance with the terms of the License.
Last updated
2025-03-28
Database
ProQuest One Academic