This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
1. Introduction
Over the past few years, transportation facilities (e.g., railroads and highways) have increasingly been extended into mountainous and hilly areas in conjunction with rapid economic and social development [1–5]. During tunnelling in such areas, rock engineers normally encounter the problem of slope stability. Statistics data shows that there are up to 148 landslides and rockfalls along the Sichuan–Tibet railway [6], and along the Dujiangyan City to Siguniang Mountain railway the stability of 32 tunnel slopes needs to be measured and evaluated [7]. Slope instabilities have threatened the safety of tunnel portals. Slope failures cause not only economic losses but also the losses of human life [8, 9]. Therefore, stability assessment and reinforcement on slope in mountainous regions are the premise for tunnel construction and operation [10].
The analysis of slope stability is a difficult task that involves the evaluation of a large number of factors, including geology, topography, slope materials, engineering activities, and rainfall [11]. In addition, a complete analysis, including geological and geomorphological fieldwork, field monitoring, and numerical modelling, is a necessary step for slope stability assessment [8]. Thus, this analysis and assessment of slope stability are crucial to the safe design and implementation of mitigation measures. Currently, slope stability can be analyzed by the limit equilibrium method, numerical methods [12, 13], and experimental methods [14]. Numerical methods, which have been widely applied to slope stability analyses, have significantly improved the speed and accuracy of slope stability analysis. In addition, the strength reduction method has gradually become a focus of theoretical research [15–17]. Various reinforcing measures (e.g., descending slopes, drainage, plugging cracks, piles, and rock bolts) have been applied to slope stabilization [18]. Stability piles and anchor frame beams are typical reinforcing measures used for large-scale slope engineering. Many researchers have studied the reinforcement mechanisms and reinforcement parameters of individual reinforcement countermeasures [19–21]. However, given the complexity of geological conditions, environmental factors, geotechnical parameters, and other factors involved in slope engineering, especially large-scale slope engineering, comprehensive reinforcement countermeasures are becoming more commonly applied. Comprehensive reinforcement mechanisms and optimization of reinforcement parameters related to slope stability await further study. In recent decades, much deposit slope engineering had been constructed [22–24]. The deposit slope is a kind of mechanical medium with complex characteristics such as discontinuity, heterogeneity, and anisotropy, which is different from common rock slope and soil slope [23]. In view of the complexity of the deposit slope problem, there is still a long way to study and solve practical engineering problems.
This case study focused on evaluating how an artificial scarp can influence the stability of a deposit slope and on evaluating the effectiveness of the four proposed reinforcement schemes. A two-dimensional (2D) finite element model was developed and combined with a shear strength analysis technique to analyze a typical deposit slope section to obtain insight into the pile–anchor–soil interaction mechanism and its contribution to deposit slope stability. The analysis was conducted using the Phase2 software. The movement of the deposit slope was monitored during construction, and the field measurements were compared to the numerical analysis results. Using a comparison analysis, we were able to perform a comprehensive evaluation of risks associated with the Taihedong tunnel deposit slope with an artificial scarp. Furthermore, we performed a reinforcement system design to ensure the safety of tunnel slope construction and operation.
2. Geological Conditions
2.1. General Description
The Taihedong tunnel, which is located in the northern Qingxin district of the city of Qingyuan in Guangdong Province, China, is a six-lane divided expressway tunnel (Figure 1). A scarp formed by manual excavation is above the tunnel exit. The scarp is 220 m long and 25 to 40 m high, and its slope ranges from 40 to 70°. The front edge of the scarp is a broad area formed by manual excavation. The right tunnel is inside the scarp, and the left tunnel is at the edge of the scarp. The supporting capacity has been seriously weakened by manual excavation at the toe of the deposit slope. The stability of the deposit slope has also diminished as deformation of the slope has occurred and tension cracks have formed as a result of excavation of the toe of the deposit.
[figure omitted; refer to PDF]
The slope materials at the tunnel exit are mainly composed of Quaternary deposits. A slope stability analysis of the tunnel exit and reinforcement of the unstable sliding mass are needed to assess the effects of surface water, underground water, and human engineering activities [25, 26] and ensure slope safety.
The potentially unstable geological body at the tunnel exit is a colluvial deposit with multilayer and multistage characteristics. This deposit can be divided into three subdomains: the existing deformation area (Zone I), a potential deformation area (Zone II), and a paleo deposit area (Zone III). The volume of the deposit is approximately 2.5 million m3 (including 0.55 million m3 in Zone I). The results of a geological survey indicate that there are eight tension cracks in the existing deformation area (Zone I). These cracks are typically 40–70 m long and 20–50 cm wide, with a maximum width of nearly 1 m. The tunnel exit is located at the front of Zone I. Reinforcement was necessary to limit the deformation of the deposit slope before the tunnel excavation.
2.2. Ground Conditions
Borehole exploration and ultra-high-density resistivity testing were performed to determine the deposit profiles, and soil samples were collected for laboratory tests. Figure 2 shows a representative cross section of the study site, based on the boring tests. The deposit slope is composed of four layers: from top to bottom, gravel soil, silty clay, fully weathered argillaceous siltstone, and strongly weathered argillaceous siltstone. The parent rock of the gravel soil is mainly strongly and moderately weathered argillaceous siltstone. Gravel, silty soil, and silty clay are interspersed with the gravel soil. The parent rock of the silty clay, which was formed by weathering of argillaceous siltstone after colluvium, is mainly strongly and moderately argillaceous siltstone. Fully weathered argillaceous siltstone had completely weathered into hard and plastic silty clay. The original structure of fully weathered argillaceous siltstone, which only retained the appearance of the original rock, was completely destroyed. The strongly weathered argillaceous siltstone, with an argillaceous silty structure, massive structural deterioration, and crack development, was broken, soft, and crushable by hand. The soil and rock properties determined from the site investigation and associated laboratory tests are summarized in Table 1.
[figure omitted; refer to PDF]
Table 1
Soil and rock properties.
Stratum | Total unit weight (kN/m3) | Friction angle (°) | Cohesion (kPa) | Young’s modulus (MPa) | Poisson’s ratio |
Gravel soil | 20 | 18 | 8 | 35 | 0.13 |
Silty clay | 19 | 12.5 | 15 | 25 | 0.25 |
Fully weathered argillaceous siltstone | 20 | 15 | 17 | 32 | 0.30 |
Strongly weathered argillaceous siltstone | 21 | 20 | 25 | 40 | 0.24 |
2.3. Potential Sliding Plane
The various types of relevant strata at the study site exhibit significant differences in their engineering geological properties and permeability. To better guide the layout of the slope reinforcement system, the results of in situ tests (boring tests, geological surveying and mapping, and ultra-high-density resistivity surveying) were analyzed to estimate the potential slip surface of the deposit slope. Weak contact surface layers have developed in the following ways between the different soil and rock layers and could be potential sliding planes. (1) A weak contact surface layer has developed between layers of silty clay and fully weathered argillaceous siltstone. The gravel soil layer of the colluvial deposit is a permeable stratum. Consequently, relatively impermeable silty clay and fully weathered argillaceous siltstone have been infiltrated by rainwater. A weak layer has formed between them. (2) A weak contact surface layer has formed between fully weathered argillaceous siltstone and strongly weathered argillaceous siltstone. Shallow landslides and surface cracks have caused rainwater infiltration. A deep sliding surface has formed between the fully weathered argillaceous siltstone and the strongly weathered argillaceous siltstone, as confirmed by the results of the boring tests and the ultra-high-density resistivity survey.
On the basis of a comprehensive consideration of the structural conditions and activity characteristics of the deposit slope, sliding surfaces can be divided into existing sliding surfaces and potential sliding surface. The deposit slope can be divided into front, middle, and rear three-stage sliding surfaces. The leading edge of these is located at the toe of the deposit slope (Figures 1 and 2).
3. Numerical Simulation Method
3.1. Computer Program for Numerical Analysis
A 2D plane strain numerical model was developed to analyze the slope stability based on the actual geological conditions at cross section 1-1, using the Phase2 software (version 8.0). One of the major features of Phase2 is finite element slope stability analysis using the shear strength reduction (SSR) method. The model was developed on the basis of the mechanical properties of the soil and rock in each stratum summarized in Table 1.
Two-dimensional six-node triangular plane strain elements were used to discretize the 1-1 profile section of the deposit slope. The deposit model was uniformly meshed, with 2,183 elements connected with 4,496 nodes. All of the elements were found to be of good quality, on the basis of several trial-and-error tests. The number of bad elements was zero [27–29]. The boundary conditions of the slope model were set to constrain movement in both the x and y directions on the lateral sides and at the base of the slope, whereas the upper slope surface was unconstrained (Figure 3). Only gravity loading was applied to the model. The ratio of the horizontal to vertical stress was maintained at 1.0 [30]. The shear strength reduction (SSR) approach, with a tolerance of 0.001, was used to determine the critical strength reduction factor (SRF) [31, 32]. This approach involves the determination of the SRF or the factor of safety (SOF) by successive reduction of the cohesion (c) and internal friction angle (φ) of the soil until failure occurs.
[figure omitted; refer to PDF]
An iterative nonconvergence failure criterion was used to determine the critical SRF [33]. The deposit slope material was considered to be an elastic and perfectly plastic substance obeying a Mohr–Coulomb failure criterion. This was controlled by keeping the peak values equal to the residual values [27, 34].
The discrete stability piles and concrete frame beams were modeled as standard linear beams with flexural rigidity [35]. The prestressed anchors were modeled as tiebacks. The anchors were modeled as fully bonded. Figure 3 illustrates the finite element model established. The properties of the structural elements are summarized in Table 2.
Table 2
Properties of structural elements adopted in the finite element model.
Prestressed anchors | Parameter | Bolt modulus | Tensile capacity | Pretensioning force |
Value | 19.5 × 104 MPa | 1041 kN/1562 kN | 183 kN/20 kN | |
Rock bolts | Parameter | Bolt modulus | Tensile capacity | Residual tensile capacity |
Value | 20 × 104 MPa | 220 kN | 123 kN | |
Concrete frame beams/stabilizing piles | Parameter | Young’s modulus | Poisson's ratio | Properties |
Value | 3.0 × 104 MPa | 0.2 | Elastic |
3.2. Stability Analysis of Original Slope
The critical SRF and displacements for natural slope debris are shown in Figure 4. The numerical simulation results show that critical SRF values of 1.015, 1.017, and 1.029 and maximum displacements of 425 mm, 510 mm, and 855 mm were obtained for the front, middle, and rear of the deposit slope, respectively, along the 1-1 profile section. The stability analysis of the middle of the deposit slope included consideration of the front of the deposit slope. The stability analysis of the rear of the deposit slope included consideration of the front and middle of the deposit slope. The results indicate that the deposit slope is in a state of limit equilibrium. The results show very good agreement with the field measurements. The deformation area is located above the artificial scarp and the tunnel exit, at the front edge of the deformation of the deposit slope. The factors of safety for the middle and rear of the deposit slope are considerably larger than that for the front of the deposit slope. Thus, the front of the deposit slope must be reinforced before excavation.
[figure omitted; refer to PDF]
Critical SRF values of 1.045 and 1.015 were obtained for schemes A and O, respectively. The safety factor for scheme A was 3.0% higher than that for scheme O. This result shows that the front stability piles provided resistance to deformation of the soil at the front of the deposit. The prestressed anchor cables improved the mechanical properties of the rock and soil. The front of the deposit was reinforced by the prestressed anchor cables and stability piles, and its stability was improved.
Critical SRF values of 1.422 and 1.045 were obtained for schemes C and A. The safety factor for scheme C was 36.1% higher than that for scheme A and 40.1% higher than that for scheme O. As discussed previously, the deformation area was located at the front edge of the deformation body of the deposit slope. The anchors and concrete frame beams provided stress compensation for the artificial scarp and restricted the upper soil from continuing to be pulled. Thus, the analysis shows that the anchors and concrete frame beams significantly improved the stability of the deposit slope.
The front prestressed anchor cables and stability piles, the rear stability piles, and the anchors and concrete frame beams displayed different degrees of reinforcement effectiveness in the slope reinforcement system. Figure 6 and Table 4 show the numerical analysis results for the four different reinforcement schemes (Table 3). For scheme D, critical SRF values of 1.428, 1.440, and 1.515 were obtained for the front, middle, and rear of the deposit slope, respectively. These factors of safety are consistent with the GB 50330-2013 standard, which specifies a value of more than 1.30 for a grade III slope. Scheme D was therefore adopted for this engineering application.
[figure omitted; refer to PDF]
As shown in Figure 10, the measured horizontal displacements of the deformation body differed from the numerical results. The reasons are as follows: (1) although monitoring hole JC01 is adjacent to the section considered in the numerical simulation, it is not in the same position, as shown in the plane layout in Figure 1. Both the measured and simulated horizontal displacements exhibit the same deformation trend, which indicates the accuracy of the simulated results to a certain extent. (2) A series of temporary measures were taken to reduce the groundwater level during the construction of the reinforcement system, which effectively improved the stability of the deposit slope. (3) Grouting reinforcement was used in a localized area above the tunnel roof during the construction of the reinforcement system. This further improved the deposit stability above the tunnel roof. The drainage holes and grouting reinforcement mentioned above were not simulated in the numerical model, but they did strengthen the reinforcement system during construction, which explains why the numerically simulated horizontal displacements were larger than the measured ones, as shown in Figure 10. The numerical simulation results were judged to be consistent with the measured results. The proposed comprehensive reinforcement scheme was therefore judged to be a suitable guide for tunnel slope reinforcement.
Figure 11 shows the displacement increment data for monitoring hole JC01 during the construction of the slope reinforcement and the initial excavation of the tunnel. The deposit slope reinforcement began in the middle of May and lasted for about two months. The tunnel excavation was carried out after the completion of the reinforcement construction. The monitoring data indicated that the horizontal displacement of the deformation body was found to increase quickly at the beginning of the reinforcement construction and tunnel excavation data. The subsequent rate of horizontal displacement was notably reduced. Before the slope was disturbed, the displacement increment was relatively small, less than 5 mm, and the slope was in the ultimate stability state. During the construction of the stabilizing piles, the excavation of the numerous pile holes disturbed the slope and caused a release of stress in the slope. The displacement of the slope tended to increase. However, no obvious deformation of the slope as a whole was observed. During the construction of the prestressed anchor cable frame beam, the displacement of the slope was significantly reduced because of the reinforcement effect of the stabilizing pile and the cessation of disturbance. After the completion of the comprehensive reinforcement construction, the whole reinforced slope was affected by the tunnel excavation. The displacement tended to increase, but the displacement values were all less than 18 mm. The displacement increase tended to be gentle as the tunnel excavation continued to advance. The whole slope was stable. In summary, the analysis results show that the comprehensive reinforcement treatment significantly improved the stability of the deposit slope and ensured the safety of the tunnel construction.
[figure omitted; refer to PDF]
The measured and simulated results together indicate that the failure mode of the deposit was a typical retrogressive landslide type [36, 37]. The failure process is as follows: the scarp formed by a long-term excavation reduced the slip resistance of the toe of the deposit slope. Significant displacement occurred in front of the deposit. The strength of the rock and soil mass was further reduced by the surface cracks and rainwater infiltration. The front of the deposit slope was in a state of limit equilibrium. If no reinforcement measures are taken, the middle and rear of the deposit slope will be driven to slide. Finally, the whole deposit slope will slide. The slope failure will cause significant property damage and harm to those in the area. As for the retrogressive landslide, the optimal reinforcement site is the lower region of the deposit slope. In this engineering application, the anchors, concrete frame beams, prestressed anchor cables, and front stability piles that were installed at the front of the deposit slope effectively enhanced the safety factor and stability of the deposit slope. The rear stability piles are able to prevent the front deposit from being pushed and the middle and rear of the deposit from being pulled.
5. Conclusions
A deposit slope at an exit of the Taihedong tunnel, which is located in the city of Qingyuan in Guangdong Province, China, was analyzed in this study. The deposit slope, with surface cracks, had a scarp formed by a long-term excavation at the toe of the slope and was in a state of limit equilibrium. To determine how to best reinforce the deposit slope, four reinforcement schemes were analyzed based on field measurements and 2D numerical analysis results. The major findings of the study can be summarized as follows:
(1) The maximum horizontal displacement and the minimum safety factor of the deposit slope with the artificial scarp formed by excavation were located at the front of the slope. The horizontal displacements of the middle and rear of the slope decreased gradually, and the safety factor increased steadily.
(2) At the beginning of the reinforcement construction, a large number of excavation piles disturbed the slope and released stress within the slope, resulting in a significant increase in horizontal displacement. The construction of the prestressed anchor cable frame beam reinforcement resulted in less disturbance to the slope. The slope was strengthened by the stability pile, and the horizontal displacement of the slope was notably reduced as a result. The tunnel excavation disturbed the reinforced slope. The horizontal displacement increased notably at first and then became more stable. At all construction stages, the slope as a whole was in a stable state.
(3) The slope stability of this retrogressive-type landslide was improved significantly by the use of prestressed anchor cable frame beam and front stability pile reinforcements, which provided stress compensation for the artificial scarp at the foot of the slope. The antisliding force of the slope was improved. The rear stability piles were found to be effective in preventing the front slope from being pushed and the middle and rear slopes from being pulled and in improving the overall stability of the deposit slope.
Acknowledgments
The authors would like to express their thanks for the financial support provided by the National Natural Science Foundation of China (Grant no. 11872287) and the Foundation of Shaanxi Key Research and Development Program (no. 2019ZDLGY01-10).
[1] G. Barla, F. Antolini, M. Barla, "Slope stabilization in difficult conditions: the case study of a debris slide in Nw Italian Alps," Landslides, vol. 10 no. 3, pp. 343-355, DOI: 10.1007/s10346-013-0396-2, 2013.
[2] K. Wu, Z. Shao, S. Qin, W. Wei, Z. Chu, "A critical review on the performance of yielding supports in squeezing tunnels," Tunnelling and Underground Space Technology, vol. 114 no. 1, 2021.
[3] K. Wu, Z. Shao, "Visco-elastic analysis on the effect of flexible layer on mechanical behavior of tunnels," International Journal of Applied Mechanics, vol. 11 no. 3,DOI: 10.1142/s1758825119500273, 2019.
[4] B. Hu, M. Sharifzadeh, X. T. Feng, W. B. Guo, R. Talebi, "Roles of key factors on large anisotropic deformations at deep underground excavations," International Journal of Mining Science and Technology, vol. 31 no. 2, 2021.
[5] K. Wu, Z. Shao, S. Qin, "An analytical design method for ductile support structures in squeezing tunnels," Archives of Civil and Mechanical Engineering, vol. 20,DOI: 10.1007/s43452-020-00096-0, 2020.
[6] Y. G. Xue, F. M. Kong, W. M Yang, "Main unfavorable geological conditions and engineering geological problems along Sichuan—Tibet railway," Chinese Journal of Rock Mechanics and Engineering, vol. 39 no. 3, pp. 445-468, DOI: 10.13722/j.cnki.jrme.2019.0737, 2020.
[7] J. P. Huang, C. W. Sun, X. Y. Wu, S. X. Ling, S. Wang, R. Deng, "Stability assessment of tunnel slopes along the Dujiangyan city to Siguniang mountain railway, China," Bulletin of Engineering Geology and the Environment, vol. 79, 2020.
[8] S. Sun, S. Li, L. Li, "Slope stability analysis and protection measures in bridge and tunnel engineering: a practical case study from Southwestern China," Bulletin of Engineering Geology and the Environment, vol. 78 no. 5, pp. 3305-3321, DOI: 10.1007/s10064-018-1362-y, 2019.
[9] K. Wu, Z. Shao, "Study on the effect of flexible layer on support structures of tunnel excavated in viscoelastic rocks," Journal of Engineering Mechanics, vol. 145 no. 10,DOI: 10.1061/(asce)em.1943-7889.0001657, 2019.
[10] N. Xu, J. Wu, F. Dai, Y. Fan, T. Li, B. Li, "Comprehensive evaluation of the stability of the left-bank slope at the Baihetan hydropower station in southwest China," Bulletin of Engineering Geology and the Environment, vol. 77 no. 4, pp. 1567-1588, DOI: 10.1007/s10064-017-1018-3, 2018.
[11] D. Q. Song, J. D. Chen, J. H. Cai, "Deformation monitoring of rock slope with weak bedding structural plane subject to tunnel excavation," Arabian Journal of Geosciences, vol. 11 no. 11,DOI: 10.1007/s12517-018-3602-7, 2018.
[12] G. Zhao, Y. Yang, H. Zhang, G. Zhang, "A case study integrating field measurements and numerical analysis of high-fill slope stabilized with cast-in-place piles in Yunnan, China," Engineering Geology, vol. 253, pp. 160-170, DOI: 10.1016/j.enggeo.2019.03.005, 2019.
[13] Q. B. Zhan, X. J. Sun, C. Li, "Stability analysis and reinforcement of a high-steep rock slope with faults: numerical analysis and field monitoring," Advances in Civil Engineering, vol. 2019,DOI: 10.1155/2019/3732982, 2019.
[14] Z. L. Sun, L. W. Kong, A. G. Guo, "Centrifuge modeling tests on seismic response of lower bedrock deposit slopes before and after reinforced with stabilizing piles," Chinese Journal of Rock Mechanics and Engineering, vol. 36 no. 6, pp. 118-128, 2017.
[15] O. C. Zienkiewicz, C. Humpheson, R. W. Lewis, "Associated and non-associated visco-plasticity and plasticity in soil mechanics," Géotechnique, vol. 25 no. 4, pp. 671-689, DOI: 10.1680/geot.1975.25.4.671, 1975.
[16] M. Pirone, G. Urciuoli, "Analysis of slope-stabilising piles with the shear strength reduction technique," Computers and Geotechnics, vol. 102, pp. 238-251, DOI: 10.1016/j.compgeo.2018.06.017, 2018.
[17] F. Tschuchnigg, H. F. Schweiger, S. W. Sloan, "Slope stability analysis by means of finite element limit analysis and finite element strength reduction techniques. part I: back analyses of a case history," Computers and Geotechnics, vol. 70, pp. 178-189, DOI: 10.1016/j.compgeo.2015.07.019, 2015.
[18] Z. Chen, Z. Wang, H. Xi, "Recent advances in high slope reinforcement in China: case studies," Journal of Rock Mechanics and Geotechnical Engineering, vol. 8 no. 6, pp. 775-788, DOI: 10.1016/j.jrmge.2016.11.001, 2016.
[19] K. Wu, Z. Shao, S. Qin, B. Li, "Determination of deformation mechanism and countermeasures in silty clay tunnel," Journal of Performance of Constructed Facilities, vol. 34 no. 1,DOI: 10.1061/(asce)cf.1943-5509.0001381, 2020.
[20] Y. Huang, X. Xu, J. J. Liu, Huang, W. W. Mao, "Centrifuge modeling of seismic response and failure mode of a slope reinforced by a pile-anchor structure," Soil Dynamics and Earthquake Engineering, vol. 131,DOI: 10.1016/j.soildyn.2020.106037, 2020.
[21] K. Wu, Z. Shao, S. Qin, N. Zhao, H. Hu, "Analytical-based assessment of effect of highly deformable elements on tunnel lining within viscoelastic rocks," International Journal of Applied Mechanics, vol. 12 no. 3,DOI: 10.1142/s1758825120500301, 2020.
[22] W. C. Cheng, G. Li, N. N. Liu, J. Xu, S. Horpibulsuk, "Recent massive incidents for subway construction in soft alluvial deposits of Taiwan: a review," Tunnelling and Underground Space Technology, vol. 96,DOI: 10.1016/j.tust.2019.103178, 2020.
[23] H. Q. Chen, R. Q. Huang, F. Lin, "Study on the spatial engineering effect of large accumulation slope," Chinese Journal of Geotechnical Engineering, vol. 27 no. 3, pp. 323-328, 2005.
[24] Z. Sun, L. Kong, A. Guo, M. Alam, "Centrifuge model test and numerical interpretation of seismic responses of a partially submerged deposit slope," Journal of Rock Mechanics and Geotechnical Engineering, vol. 12 no. 2, pp. 381-394, DOI: 10.1016/j.jrmge.2019.06.012, 2020.
[25] Y.-S. Song, W.-P. Hong, K.-S. Woo, "Behavior and analysis of stabilizing piles installed in a cut slope during heavy rainfall," Engineering Geology, vol. 129-130, pp. 56-67, DOI: 10.1016/j.enggeo.2012.01.012, 2012.
[26] G. Bicocchi, V. Tofani, M. D’Ambrosio, "Geotechnical and hydrological characterization of hillslope deposits for regional landslide prediction modeling," Bulletin of Engineering Geology and the Environment, vol. 78 no. 7, pp. 4875-4891, DOI: 10.1007/s10064-018-01449-z, 2019.
[27] V. Gupta, R. K. Bhasin, A. M. Kaynia, "Finite element analysis of failed slope by shear strength reduction technique: a case study for Surabhi Resort Landslide, Mussoorie township, Garhwal Himalaya," Geomatics, Natural Hazards and Risk, vol. 7 no. 5, pp. 1677-1690, DOI: 10.1080/19475705.2015.1102778, 2016.
[28] I. Jamir, V. Gupta, V. Kumar, G. T. Thong, G. T. Thong, "Evaluation of potential surface instability using finite element method in Kharsali Village, Yamuna Valley, Northwest Himalaya," Journal of Mountain Science, vol. 14 no. 8, pp. 1666-1676, DOI: 10.1007/s11629-017-4410-3, 2017.
[29] D. P. Kanungo, A. Pain, S. Sharma, "Finite element modeling approach to assess the stability of debris and rock slopes: a case study from the Indian Himalayas," Natural Hazards, vol. 69 no. 1,DOI: 10.1007/s11069-013-0680-4, 2013.
[30] P. Shilpa, M. K. Amir, K. B. Rajinder, D. K. Paul, "Earthquake stability analysis of rock slopes: a case study," Rock Mechanics and Rock Engineering, vol. 45, pp. 205-215, 2012.
[31] T. Matsui, K. C. San, "Finite element stability analysis method for reinforced slope cutting," Proceedings of the International Geotechnical Symposium on Theory and Practice of Earth Reinforcement, pp. 317-322, .
[32] T. Matsui, K.-C. San, "Finite element slope stability analysis by shear strength reduction technique," Soils and Foundations, vol. 32 no. 1, pp. 59-70, DOI: 10.3208/sandf1972.32.59, 1992.
[33] T. K. Nian, G. Q. Chen, S. S. Wan, M. T. Luan, "Non-convergence criterion on slope stability FE analysis by strength reduction method," Journal of Convergence Information Technology, vol. 6 no. 5, pp. 78-88, 2011.
[34] D. V. Griffiths, P. A. Lane, "Slope stability analysis by finite elements," Géotechnique, vol. 49 no. 3, pp. 387-403, DOI: 10.1680/geot.1999.49.3.387, 1999.
[35] G. Tiwari, G. M. Latha, "Design of rock slope reinforcement: an himalayan case study," Rock Mechanics and Rock Engineering, vol. 49 no. 6, pp. 2075-2097, DOI: 10.1007/s00603-016-0913-4, 2016.
[36] J. W. Zhang, Y. Zou, Y. L. Li, "Failure mechanism and stability analysis of big multi-layer deposit," Chinese Journal of Rock Mechanics and Engineering, vol. 35 no. 12, pp. 2479-2489, 2016.
[37] G. H. Yang, Z. H. Zhong, Y. C. Zhang, E. Q. Wang, "Dentification of landslide type and determination of optimal reinforcement site based on stress field and displacement field," Chinese Journal of Rock Mechanics and Engineering, vol. 31 no. 9, pp. 1879-1887, 2016.
You have requested "on-the-fly" machine translation of selected content from our databases. This functionality is provided solely for your convenience and is in no way intended to replace human translation. Show full disclaimer
Neither ProQuest nor its licensors make any representations or warranties with respect to the translations. The translations are automatically generated "AS IS" and "AS AVAILABLE" and are not retained in our systems. PROQUEST AND ITS LICENSORS SPECIFICALLY DISCLAIM ANY AND ALL EXPRESS OR IMPLIED WARRANTIES, INCLUDING WITHOUT LIMITATION, ANY WARRANTIES FOR AVAILABILITY, ACCURACY, TIMELINESS, COMPLETENESS, NON-INFRINGMENT, MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE. Your use of the translations is subject to all use restrictions contained in your Electronic Products License Agreement and by using the translation functionality you agree to forgo any and all claims against ProQuest or its licensors for your use of the translation functionality and any output derived there from. Hide full disclaimer
Copyright © 2020 Yong Hong et al. This is an open access article distributed under the Creative Commons Attribution License (the “License”), which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. Notwithstanding the ProQuest Terms and Conditions, you may use this content in accordance with the terms of the License. https://creativecommons.org/licenses/by/4.0/
Abstract
This paper presents the results of the stability analysis of a deposit slope with an artificial scarp in a tunnel exit and an evaluation of the effectiveness of four proposed reinforcement schemes. A typical slope section was used to study the deposit slope stability and retaining mechanisms of the reinforcement systems. A series of two-dimensional (2D) finite element models (FEM), combined with a strength reduction technique, was established using the Phase2 software. According to field monitoring results, the horizontal displacements of the front, middle, and rear of the slope decreased gradually, and the safety factor increased successively. The front of the deposit slope was in a state of limit equilibrium as a result of the artificial scarp formed by long-term manual excavation. Anchors and concrete frame beams provided stress compensation and improve the stability of the deposit slope, and front prestressed anchor cables and stability piles strengthened the mechanical properties of the rock and soil masses and provided resistance at the front of the deposit. Rear stability piles prevented the front of the deposit from being pushed and the middle and rear of the deposit from being pulled and provided resistance at the front of the deposit. The field monitoring also showed that the deformation of the deposit slope was effectively controlled. The study results provide insights into the effectiveness of measures for reinforcing and maintaining the stability of deposit slope with artificial scarps.
You have requested "on-the-fly" machine translation of selected content from our databases. This functionality is provided solely for your convenience and is in no way intended to replace human translation. Show full disclaimer
Neither ProQuest nor its licensors make any representations or warranties with respect to the translations. The translations are automatically generated "AS IS" and "AS AVAILABLE" and are not retained in our systems. PROQUEST AND ITS LICENSORS SPECIFICALLY DISCLAIM ANY AND ALL EXPRESS OR IMPLIED WARRANTIES, INCLUDING WITHOUT LIMITATION, ANY WARRANTIES FOR AVAILABILITY, ACCURACY, TIMELINESS, COMPLETENESS, NON-INFRINGMENT, MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE. Your use of the translations is subject to all use restrictions contained in your Electronic Products License Agreement and by using the translation functionality you agree to forgo any and all claims against ProQuest or its licensors for your use of the translation functionality and any output derived there from. Hide full disclaimer