This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
1. Introduction
In the modern transportation system, the railway had green advantages in large capacity and low carbon and is still in the development stage [1, 2]. Railway construction activities bring negative environmental impacts [3], like resource and energy consumption, pollution and waste discharge, ecological landscape cutting, and destruction [4, 5], etc. At the same time, the railway product can bring positive environmental impacts, including direct benefits such as green corridor construction, the outstanding effect of land saving, energy-saving and emission reduction, and indirect ecological benefits such as innovation and upgrading of environmental protection technology and optimization of land development pattern [6]. The fundamental purpose of green railway engineering (GRE) [7] is to alleviate or absorb negative ecological effects and improve or expand positive environmental effects. Based on the long-term engineering practice, amounts of measures have been summarized or innovated, which can solve the negative environmental impact of railway construction, including clean energy use, renewable resources use, waste reduction [8], the active degradation of waste discharge standards, avoiding ecologically sensitive areas, planning vegetation system, setting up biological channels, and so on [9]. However, it is easy to ignore the economy [10] and standardization [11] of green governance under the guidance of the current evaluation index that focuses on results rather than process. At the same time, the current green evaluation index system has vague cognition and in-systematic of the green innovation and does not highlight the positive environmental effect and contribution subject of green innovation. Otherwise, the incentive effect of evaluation is not good.
Therefore, it is necessary to construct a new GDR index to reflect the green governance effect from whole process, deconstruction GRE system to reveal the practice process, and clear key factors and their responsibility body of GDR in order to provide theoretical basis to solve such problems as the economy, standardization, systematization, and incentive.
2. Literature Review and Concept Definition: Green Degree of Railway Engineering (GDR)
Green degree was early applied in the field of mechanical engineering and was defined as “a comprehensive evaluation index for the input of resources and energy, the output of environment and the friendliness of these inputs and outputs to the environment in the whole life cycle of a product” [12]. As the concept spread of sustainable development, the concept of green degree is widely used in other fields, such as a green degree of chemical process, the green degree of enterprise, the green degree of the supply chain, and so on. There are also some green degree studies in the field of engineering construction, and related concepts are shown in Table 1.
Table 1
Definition and evaluation indexes of various green degrees in the engineering construction field.
| Name | Definition | Evaluation index |
| Green degree of building | Evaluation criteria used to describe the degree of harmony between buildings and the environment and the degree of construction rationalization [13] | Safe and durable, healthy and comfortable, convenient life, resource-saving, livable environment [13] |
| Green degree of highway | In the whole life cycle, adhere to the concept of green development, protect the ecological environment, improve the quality of the project, save intensive resources and improve the degree of service quality [14] | Green concept, ecological environmental protection, resource conservation, quality construction, service improvement [14] |
| Green degree of construction | In the whole process of construction to achieve green development, low-carbon environmental protection, resource cycle of the green degree [15] | Energy resources, environmental protection, construction management, technological innovation, and social coordination [15] |
| Green degree of materials | It is used to measure the applicability of sand concrete with different litho logic mechanisms to railway engineering in complex and dangerous mountainous areas [16] | Performance, economic benefits, social benefits, environmental impact, production technology [16] |
| Green degree of temporary facilities | The degree of energy-saving, environmental protection, turnover, and efficient production in the whole life cycle [17] | Balanced ecological environment, scientific space layout, reasonable construction economy, coordinated management, and operation [17] |
There are two common points in the above concepts: first, “green degree” is a concept to measure the comprehensive achievement of green goals of something; Secondly, quality, environment, and resources are the core elements of “green degree.”
There are also two weaknesses: First, although most definitions emphasize the premise of “whole process” or “whole life cycle,” each concept essentially reflects a static final result and lack of attention to the process of achieving the process and the changing rules. Second, from the perspective of green degree index content, it mainly reflects the specific needs of green goals while lacking the disclosure of essential elements.
System dynamics is widely used to solve complex and dynamic problems in construction management [18], such as construction waste reduction mechanism research [19], construction risk management research [20], and so on. The GDR is a composite concept composed of different indicators, which have different cause mechanisms and variation trends and have cross-influence in practice [21]. Therefore, the SD method also can be applied to explore the change process of GDR.
Based on the environment-economy large-scale system model [22], the natural environment is the support system for the normal operation of the social economy, mainly inputting resources into the economic system and absorbing the wastes produced by the economic system. Based on the recycle economy theory [23], renewable resources can effectively supplement the resource demand of the economic system, thus reducing the demand for natural resource exploitation. Therefore, environmental protection and resource conservation are the essential needs of the green goal. Based on the concept consensus and research weaknesses of “green degree,” “green degree of Railway Engineering” (GDR) is defined as “the comprehensive reaching effect of environmental protection and resource conservation in the whole process of railway engineering construction,” which aims to reflect the practical process of a railway engineering project and the fitting degree with expected of engineering product.
This concept emphasizes the requirement of measuring GDR both from the actual control value (VA) and the expected control value (VE) of the green target, while further analysis of the green object remains to be solved. Generally speaking, environmental protection is embodied in controlling and reducing environmental costs, including natural ecological protection (such as green corridors [24]) and pollution control of engineering activities. Resource-saving is reflected in the control and reduction of resource cost, including the optimization of land occupation (such as the combination of permanent and temporary [25], the integration of station and city [26]) and the control of production consumption (resource utilization of tunnel dregs [27]). Refer to the Code for Environmental Protection Design of Railway Engineering (TB 10501-2016), Evaluation Standard for Green Railway Stations (TB/T 10429-2014), evaluation Standard for Green Construction of Construction Engineering (2018 Draft for Comments), etc., the classification of GDR indexes is shown in Figure 1.
[figure(s) omitted; refer to PDF]
As shown in Figure 1, the ecology protection index is aimed at the natural elements, such as animals and plants, water and soil environment, geological environment, etc. Habitat cutting and secondary disasters are the prominent characteristics of linear engineering environmental impact. Pollution regulation focuses on engineering construction pollutants, such as noise, dust, solid waste, wastewater, and others, which have similar characteristics to other civil engineering construction pollutants, but the generated engineering waste components have their own characteristics [28]. The land resources index is targeted at the carrier of engineering and construction activities, the control of land resources occupation is a prominent feature of linear engineering, while the occupation optimization of large temporary engineering is a prominent feature of railway engineering [29]. The production resource index is aimed at the control of consumable resources needed for construction and production; railway engineering has outstanding characteristics in resource consumption and mechanical energy consumption [29].
3. The Destructive for GRE System: Based on the “Input-Output” Relationship
GRE system is an “input-output” system. The input elements included green knowledge system, green talent system, material resource system, and natural ecosystem, which is constructed and produced by engineers and takes the new artificial natural system as the main output target. The relationship is shown in Figure 2.
[figure(s) omitted; refer to PDF]
3.1. Input Elements
Inputs can be divided into 4 systems: (1) Green knowledge system is a knowledge collection required by GRE practice, such as geological and hydrological exploration data besides the line regional, environmental impact assessment report, green environmental protection technology, and so on. It is the basis for green schemes [30] formulated by participants, which mainly include green design scheme, green construction scheme, and green planning scheme, as shown in Table 2. (2) Green talent system is a collection of all kinds of talents required by green engineering practice, which has a certain identity with the green knowledge system. (3) Natural ecosystem is the carrier space of engineering practice, including geology, hydrology, flora, and fauna, etc. (4) Engineering resource system is a collection of resources required by engineering practice, including capital, raw materials, energy, and so on.
Table 2
Task and content of green schemes.
| Type | Task | Content |
| Green design scheme (including preliminary design, technical design, and construction design) [31] | Green design of engineering structure | Reduce the occupation of cultivated land, strengthen the design of disaster prevention and mitigation, improve the health and durability of the project, implement the function of energy conservation and emission reduction; taking the systematic design of engineering and environment as an opportunity to intervene in the comprehensive management of ecological restoration and promote the harmonious coexistence of engineering and human activities |
| Green design of temporary engineering | Design temporary engineering from the perspectives of sustainable use of the site, permanent and temporary integration, convenient transportation, and emission reduction | |
| Green design of environmental protection facilities | Ensure the realization of green production in railway operation and solve environmental problems such as waste discharge management, vibration noise elimination, electromagnetic radiation barrier, and so on | |
| Green construction scheme (construction organization design, clear resource allocation, production layout, technology, etc.) [32] | Disturbance control | Reduce the disturbance or damage to the natural environment caused by construction operations |
| Resource-saving | Improve the efficiency of resource utilization and strengthen resource management | |
| Pollution prevention and control | Reduce the discharge of pollutants in construction operations, treat the output pollutants, and discharge them to standards | |
| Ecological remediation | Site restoration, planting grass, and trees, etc. | |
| Labor conservation and protection | Environmental protection education, environmental protection skills training, environmental protection theme activities, green operation environment construction, etc. | |
| Green planning scheme | Green knowledge innovation plan | The establishment of scientific research projects aiming at the knowledge blind spots and difficult problems of green knowledge reserve usually depends on the needs of national scientific research plans or projects |
| Green culture creative plan | In order to promote group cohesion, cultural unity action should be carried out aiming at the pluralism of group ideology of participants in engineering practice | |
3.2. Output Elements
The actual output can be divided into 1 system and 3 products, which are related to the socioeconomic system, green knowledge (talent) system, and material resource system, respectively. (1) The combination of railway engineering entities and the natural environment forms a new artificial natural system, which plays a service role in the socioeconomic system and is the core purpose of engineering practice; (2) based on engineering innovation, new green knowledge (such as principle, process, technology, system, etc.), new green culture, can be produced to enrich the content of green knowledge system and train new green talents at the same time; (3) all kinds of wastes (such as wastewater, waste gas, waste materials, dust, hole slag, etc.) are generated by the construction of the project, part of the recyclable substances supplement (or exchange) the reserves of the engineering resource system through recycling and utilization, and the rest are directly emission into the natural ecosystem after degradation treatment (or removed from the region).
3.3. Engineering Practice System
Engineering practice system whom Linked inputs and outputs are a subjective active system based on the design and construction unit’s own resources (talent team, engineering equipment, technical reserve, etc.) and is also a key part to determine the GDR, so it is the object of further research. From the spatial characteristics, railway engineering is a linear layout, and its construction organization usually divides the project into sections and pushes forward in one direction within a certain project. From the engineering management characteristics, railway construction projects are uniformly managed by construction units, and reliable and applicable advanced technology construction methods will be promoted across the whole line, thus promoting technological upgrading by comprehensive. Therefore, in the engineering system, a feedback path based onstage status assessment can be established, and an iterative upgrade of green elements in engineering system can be realized based on this path, as shown in Figure 3.
[figure(s) omitted; refer to PDF]
4. Model Construction: Based on the System Dynamic Method
4.1. System Boundary and Object Analysis
Based on the structural relationship of the GRE system (Figure 2), the engineering practice system is the main object to be deeply studied. It takes project approval as the starting point, completion acceptance as the endpoint, and railway engineering enterprises as the main body, involving three stages of planning, design, and construction. Each stage has different leaders and core stakeholders [33], which are different from stakeholders of other professions [34]. From the nature of work at each stage, green planning and green design only provide corresponding schemes but have not entered into engineering practice yet. Green construction involves two different works of different natures, namely scheme formulation and concrete implementation. All formulated schemes provide guidance for the concrete implementation of engineering projects, as shown in Figure 4.
[figure(s) omitted; refer to PDF]
Based on Figure 1, the corresponding problems are ecological damage, environmental pollution, land occupation and resources consumption, etc., which are the main observation objects of GRE. Based on Figure 3, the control values of the above green observed objects are given by the green schemes, as shown in Figure 5.
[figure(s) omitted; refer to PDF]
As shown in Figure 5, there are some detailed explanations.
Ecological damage reflects the destruction of the original ecosystem elements during construction, such as roadbed excavation, vegetation removal, and opening up of active areas, which usually leads to soil erosion, animal and plant diversity damage, and secondary disasters are more likely to be caused by extreme climate or geological activities [35]. Most of these activities occur in the construction preparation stage (such as temporary engineering) and also exist in the construction and production stage, such as tunnel excavation, bridge pile foundation, and excavation of abandoned soil fields. The observation of “ecological damage degree” is to ensure that the engineering activities are within the controlled range of natural carrying capacity, will not cause irreversible ecological harm (such as desertification, loss of biodiversity, etc.), and reduce the difficulty of ecological restoration.
Environmental pollution reflects the production and emission of pollutants, major pollutants including wastewater [36], waste gas emissions (from mechanical), dust, solid waste, living garbage, and so on, mainly caused by water pollution, soil pollution, air pollution, and other issues. This kind of activity runs through the whole construction process, but there are differences in environmental hazard degree and recyclable characteristics of various pollutants [37], which need to be classified and discussed. “Environmental pollution degree” is measured to ensure that emissions are within the limits of the natural carrying capacity [38] and do not incur high remediation costs (such as fines).
Land occupation is one of the focal points of the contradiction between development and protection, and the railway engineering has an important impact on the areas related to ecological security [39], such as nature reserves, cultivated land, and so on, such as cutting and occupation from the ecological perspective, and regional industrial planning from the economic perspective. Land issues focus on permanent occupation and temporary occupation. The former focuses on intensive land use (station) and land saving (line), and the latter focuses on the restoration of land function and permanent-temporary integration (construction and development cooperation). The observation of “land occupation degree” is to control the occupation amount of construction land within the approved scope of project construction land so as not to cause more than expected occupation situation, and at the same time, to timely summarize the key measures conducive to land saving (such as replacing roads with Bridges) and promote as appropriate.
Resource consumption is one of the concerns of the global resource and energy crisis and also the key point of cost control. Resources include raw materials (sand, cement, steel, etc.), energy (oil, electricity, etc.), water, etc. Construction production needs to consume a huge amount of raw materials, while many reasons will cause resource loss like engineering technology, mechanical efficiency, materials transportation, process management, and so on. The resource loss not only produces a large amount of waste but also affects ecological security. The observation of “resource consumption degree” is to ensure that the consumption degree of production materials is within the scope of the resource use plan. On the one hand, the overconsumption behavior [40] is found in time, and the response is made to avoid the delay phenomenon caused by the shortage of production materials [41]. On the other hand, summarize the key measures conducive to resource-saving (such as intelligent control, process optimization, etc.) and promote them as appropriate.
4.2. Causality Analysis
There are two types of causality in the causality diagram. One is the “strong to strong” positive influence relationship, which is represented by the symbol “+,” The variable B pointed to by the arrow will have the same change direction as the variable A sent by the arrow (A increases, B increases too). The other is the “strong to weak” or “weak to strong” negative influence relationship, denoted by the symbol “−,” the variable B that the arrow points to will have the opposite change direction with variable A sent by the arrow (A increase, B decrease). The causality arrow line mainly represents the direction of knowledge flow, information flow, and material flow.
4.2.1. Overall Causality of GRE System
Combined with Figures 3 and 4, draw the causal diagram of the GRE system. (1) Green demand is the starting point of practice. On the one hand, it comes from ecological environment conditions and is negatively related to ecological environment carrying capacity. On the other hand, it comes from green development policy and is positively correlated with policy requirements. (2) Green scheme is the concrete implementation of green demand, mainly based on the current resource conditions, knowledge reserve, and talent reserve to make a scheme, including green design scheme and green construction scheme;. At the same time, the green scheme is a knowledge product, and the knowledge blind spot will lead to the demand for green innovation so as to realize the optimization and adjustment of the green scheme. Knowledge blind spot is negatively correlated with the total amount of green knowledge reserve. (3) Construction production is the practical application of the green scheme, so the green degree of construction production is positively correlated with the green scheme. However, due to subjective and objective reasons, the actual situation is different from the expected plan. When the green degree of construction production cannot meet the expected plan, the demand for knowledge innovation and cultural creation will be stimulated. Among them, knowledge innovation is conducive to the optimization and adjustment of green schemes, while cultural creation is conducive to the cultivation of green culture with leadership, affinity, and cohesion, so as to stimulate green construction behavior. (4) Finally, the practical result is the common result of green scheme and green construction production, which is conducive to improving ecological environment carrying capacity, increasing green knowledge reserve, and cultivating new talents with green consciousness and knowledge. The causal relationship between the above elements, the feedback loops involved, and their polarity is shown in Figure 6.
[figure(s) omitted; refer to PDF]
Because the negative feedback loop has a clear observation point and adjustment means, the balance can be achieved through feedback adjustment, while the positive feedback loop cannot achieve balance but can only promote its benign development through subjective initiative, and this benign development is the key to further promote the green degree of engineering. In Figure 6, green knowledge reserve and green talent reserve are the keys to the positive feedback loop, and the green degree of construction is the key to the negative feedback loop.
4.2.2. Causality of Green Construct Production Process
Further analyze the production practice of green construction to understand the observation object of green construction and its causal relationship. Based on Figure 5, ecological damage degree, environmental pollution degree, land occupation degree, and resource consumption degree are analyzed.
Ecological damage is the result of demolition. The purpose of demolition is to prepare engineering carriers and work sites for engineering construction activities, mainly including site preparation, pile foundation excavation, tunnel excavation, soil collection, and abandonment, etc. Engineering wastes (such as tunnel dregs and surface soil, etc.) will be produced in the demolition process. Therefore, the ecological damage degree depends on the implementation of the established design scheme and construction scheme. For pile foundation excavation, the excavation area is determined by the design scheme, and the disturbance of excavation to the surrounding environment is determined by the construction scheme, and the control value of damage degree is determined by the established design scheme and construction scheme. When the ecological damage degree reaches or exceeds the damage control value, measures should be taken according to the situation to optimize and adjust the construction scheme or demolition behavior so as to ensure the control of the degree of ecological damage. The causal relationship is shown in Figure 7.
[figure(s) omitted; refer to PDF]
Environmental pollution during the construction period is the result of the discharge of nondegradable pollutants in the construction and production, so the environmental pollution degree depends on the deviation between the pollutants produced and the abatement result in the implementation of the established construction scheme and has nothing to do with the design scheme. Due to the limited capacity of the natural ecosystem to absorb pollutants, it is necessary to control the total amount of pollutants to protect the normal function of the ecosystem. The control value is based on the setting of ecological environment carrying capacity and will be reflected in the construction plan. When the environmental pollution reaches or exceeds the pollution control value, measures should be taken according to the situation to optimize and adjust the construction plan or production behavior, curb pollution discharge or strengthen pollution control so as to ensure the control of environmental pollution. The causal relationship is shown in Figure 8.
[figure(s) omitted; refer to PDF]
Land is the carrier of engineering and the site of construction activities. The permanent occupation of land resources is the result of the construction of engineering entities, while the temporary occupation is the result of the temporary construction of engineering production. The total occupied area is determined by the design scheme. After the completion of the project, the temporary land needs to be restored to its original function or converted to other uses, which is mainly reflected in the construction plan. The scope of construction land approved by the state sets the control value for the occupation of land and resources, which is also reflected in the design scheme. With the advancement of construction and production, green awareness and green knowledge are more abundant, or the actual occupation degree is out of control, it is necessary to carry out dynamic adjustments of the design and construction scheme according to the situation. The causal relationship is shown in Figure 9.
[figure(s) omitted; refer to PDF]
Resource consumption is the inevitable result of construction production. In the process of transforming materials into engineering entities, engineering waste will inevitably be generated. The consumption of engineering resources is determined by the design scheme, while the rate of material loss is affected by the construction scheme. In addition, part of the engineering waste (hole residue, waste water, etc.) generated during engineering practice can be recycled and used to supplement production materials. When the consumption of production materials reaches or exceeds the consumption control value, measures should be taken according to the situation to optimize and adjust the construction plan or production behavior so as to control the consumption of resources. The causal relationship is shown in Figure 10.
[figure(s) omitted; refer to PDF]
The above causality includes both a positive feedback loop and a negative feedback loop, in which all the factors leading to the deterioration of the observed object (deteriorating factors) exist in the positive feedback loop, and the balance cannot be achieved. The factors that improve the observed object (the improvement factor) all exist in the negative feedback loop, and the balance can be achieved. This suggests that aggravating factors are more important to be controlled than improving factors.
4.3. Parameter and Equation Design
Based on causality analysis and system dynamics (SD) parameter types, the design parameters of the GRE system are shown in Table 3.
Table 3
Parameter list of GRE system.
| Type | Character | Name | Symbol |
| Level variable (L) | A variable that determines the behavior of the system over time. The value of the current moment is equal to the value of the past moment plus the change in time over time | Ecological damage degree | L1 |
| Environmental pollution degree | L2 | ||
| Land occupation degree | L3 | ||
| Resource consumption degree | L4 | ||
| Rate variable (R) | A variable that directly changes a level variable, reflecting the speed at which the state variable is input or output | Environment damage rate | R11 |
| Ecological restoration rate | R12 | ||
| Pollution emission rate | R21 | ||
| Pollution treatment rate | R22 | ||
| Land occupancy rate | R31 | ||
| Release occupancy rate | R32 | ||
| Resource consumption rate | R41 | ||
| Auxiliary variable (A) | Variables that affect the system but do not directly control the level variable have independent values at each time | Green schemes | A1 |
| Control values from green schemes | A11∼A14 | ||
| Green knowledge innovation | A21 | ||
| Green culture creative | A22 | ||
| Deviations form level variable | A31∼A34 | ||
| Engineering garbage | A4 | ||
| Garbage recycling | A41 | ||
| Wastage | A42 | ||
| External variable (E) | It varies over time but not by any other variable in the system | Eco-environmental carrying capacity | E1 |
| Green resource conditions | E2 | ||
| Green knowledge reserve | E3 | ||
| Green talent reserve | E4 | ||
Based on the character of different SD parameter types, the correlation between parameters is shown in Figure 11. That is, the level variable is the core observation object of the system. Rate variables directly control level variables. Auxiliary variables can affect rate variables or be constructed based on needs. The influence of external variables on the system is mainly exerted on auxiliary variables and is not affected by internal variables.
[figure(s) omitted; refer to PDF]
Therefore, according to the character of variables and their causality, the following parameter equation can be constructed:
(1) Level variable equation
Notice: T is the construction duration of a complete project or a relatively independent partial project (such as a bridge), which is determined according to the observation range of the research object.
(2) Rate variable equation
Notice:
(3) Auxiliary variable equation
Notice:
4.4. SD Model for GRE Practice Process
On the basis of parameter definition and causality, the system dynamic flow diagram is established to reflect the overall practice process of GRE and also reflect the changing process of GDR, as shown in Figure 12.
[figure(s) omitted; refer to PDF]
5. Results and Discussion
5.1. The Characteristic Analyses for GRE Practice Process
As shown in Figure 12, the important characteristics of GRE practice can be analyzed through the nature, position, and interaction between variables. With state variables as the center, this paper expounds on the causal relationship, feedback link, critical path control, and other aspects successively.
5.1.1. Give Priority to Controlling Deteriorate Factors: R11, R21, R31, R41
On the one hand, the deteriorate factor is preaction, and the improvement factor is postaction. Preaction control has significant advantages over post-action disposal, which is also conducive to cost control. On the other hand, the loop where the deteriorate factors are located is a mainly positive feedback loop, which will lead to the deterioration or even collapse of the system, like the out of control in cost or irreversible ecological damage at the worst.
5.1.2. Control Value Setting and Level Variable Observation Determine the Effectiveness of Feedback Mechanism: A11∼A14, L1∼L4
The control value (A11∼A14) is reflected in the green scheme (A1), which needs to maintain a certain stability. However, with the deepening of practice and the increase of cognition, there is also an objective, practical need for optimization and adjustment, but there is an upper limit to protecting environmental carrying capacity so as to maintain the self-regulation function of the ecosystem. Level variables (L1∼L4) usually reflect the actual situation, but due to the need for prevention and management, prediction and judgment should be made based on their development rules so that measures can be taken in advance to control or reverse the deterioration trend in time.
5.1.3. Significant Gathering Points that Control the Critical Path: A1, A21, A22
The name of 3 points can be found in Table 3. They are green scheme (A1), the function gathering point of exogenous variables and internal variables of the system; green knowledge innovation (A21) and green culture creation (A22), the aggregation point that makes up the feedback loop. According to its location and direction of the arrow line, the green scheme is the green foundation of GDR, while green knowledge innovation and green culture creation are the key factors to improving GDR.
5.1.4. Two Kinds of Improving Path: by A21 and A22
Firstly, green knowledge innovation (A21) can promote the optimization and adjustment of the green scheme to improve the GDR, which is the all-around “quality” improvement (L1∼L4). However, there is a delay effect in this path, mainly because there is a process of demonstration and promotion in the practical application of green knowledge innovation results. The second is to improve the GDR by promoting the optimization and adjustment of some deteriorate factors (R11, R21, R41) through green culture creation (A22), which is the improvement of targeted (L1, L2, L3) “quantity” without delay effect.
5.1.5. Planning and Initiative Are Necessary for GDR Improving: E3, E4, and A31∼A34
Green knowledge innovation and green culture creation are influenced by two kinds of system parameters. In terms of green knowledge innovation (A21), real-time innovation caused by deviation (A31∼A34) has a longer delay effect. The planned innovation based on the weakness of green knowledge reserve (E3) can make full use of the noncritical path of schedule arrangement and shorten the delay effect of achievement application effectively. As far as green culture creation (A22) is concerned, the demand for green culture based on the diverse consciousness of green talent reserve and the unified ideology is more comprehensive and can be gradually deepened and assimilated with the engineering practice. The demand for immediacy culture caused by the deviation is more targeted and can effectively supplement the green culture of the project.
In general, the GRE practice process based on system dynamics modeling further reveals the core of the green target is to control ecological damage, environmental pollution, and optimization of land occupation and promote the resource-saving. The key link of control is condition monitoring; a green scheme sets a good foundation for the GDR, and green knowledge and green culture promote GDR improvement through two kinds of paths, respectively.
5.2. The Promotion Strategy for GDR
Based on the analysis of characteristic in Section 5.1.4, the GDR promotion strategy is mainly proposed from two aspects of source optimization and dynamic optimization. The former strategy comes from characteristic in Section 5.1.5, while the latter strategy comes from characteristic in Section 5.1.1.
5.2.1. Source Optimization Strategy for GDR
Source optimization takes green scheme optimization as its main target and is realized by controlling or optimizing its influencing factors. The causes tree of A1 is shown in Figure 13.
[figure(s) omitted; refer to PDF]
Green schemes include green design scheme, green construction scheme, and green planning scheme (Table 2), which lay a foundation for the GDR from three aspects of green function, green implementation, and green support, respectively. Relevant source optimization strategies are shown in Table 4.
Table 4
Source optimization strategy of GDR.
| Influence factor | Green scheme | ||
| Green design scheme | Green construction scheme | Green planning scheme | |
| Environmental carrying capacity (E1) | Deepen hydrogeological survey, deepen environmental impact assessment, optimize damage control value and pollution control value standards, and determine the baseline control basis | Implement the comments on environmental impact assessment actively, and propose construction plans with less disturbance, less pollution, and faster repair | / |
| Green resource conditions (E2) | Apply new technology, new materials, etc. to design engineering structure, optimize occupation control value and consumption control value, and determine the baseline control basis | Apply new technology, new equipment, and other construction organization design, the development of small disturbance, low pollution, less waste, excellent treatment of the construction scheme | Set up green innovation research projects appropriately ahead of schedule |
| Green knowledge reserve (E3) | |||
| Green talent reserve (E4) | Increase the proportion of green designers with green knowledge and practical experience, deepen the effect of green design | The proportion of green construction personnel with rich green knowledge and practical experience should be increased to promote the group’s green ideology and awareness | Overall planning of green knowledge training and education, the establishment of incentive mechanism |
| Green knowledge innovation (A21) | Promote and apply innovative achievements in time to optimize design schemes | Promote and apply innovative achievements in time to optimize the construction plan | / |
5.2.2. Dynamic Optimization Strategy for GDR
Dynamic optimization is realized by controlling or optimizing the influencing factors of the green observation object. The causes tree of Level variables and deviations is shown in Figure 14.
[figure(s) omitted; refer to PDF]
Since the Level variable is only controlled by the rate variable, the dynamic optimization strategy of the Level variable is mainly proposed from the deteriorate factor and improvement factor. The Rate variable depends on two factors: construction scheme guidance and construction behavior management. The specific dynamic optimization strategy and its target are shown in Table 5.
Table 5
Dynamic optimization strategy of GDR.
| Level variable | Influence factor | |
| Deteriorate factor management | Improvement factor management | |
| Ecological damage degree (L1) | Decrease R11: ①Optimization of construction technology based on green knowledge innovation achievements to reduce the disturbance range and frequency | Increase R12: Improve vegetation restoration ability and reduce soil erosion based on green knowledge innovation (using science and technology to protect the environment) |
| ②Through the green culture creation to improve the awareness of green environmental protection, reduce the damage intensity of operation behavior | ||
| Environmental pollution degree (L2) | Decrease R21: ①Optimize construction technology and use green materials based on green knowledge innovation achievements to reduce the rate of pollutant generation | Increase R22: Based on the achievements of green knowledge innovation, the ability of pollutant collection and treatment should be improved, and the equipment and process of pollutant treatment should be innovated |
| ②Strengthen the management of pollution sources, establish the pollutant statistical ledger, find its statistical rules to determine the reasonable pollutant treatment threshold | ||
| Land occupation degree (L3) | Control R31: Based on the green knowledge innovation achievements, the proportion of bridge and tunnel and the building limit of the project were optimized, and the layout scheme of temporary engineering was optimized to reduce the occupation of rare land resources | Increase R32: Based on the green knowledge innovation achievements, the proportion of permanent and temporary combination design of temporary engineering was improved, and the use conversion paradigm of temporary engineering was explored to improve the level of land resource recovery and reuse |
| Resource consumption degree (L4) | Decrease R41: ①The application of advanced equipment and information technology to assist production, achieve accurate discharge, and reduce the speed of resource consumption | Increase A41: Innovation of engineering waste recycling and reusing technology, improve the recovery capacity, improve the capacity of local materials use |
| ②Establish resource consumption and consumption ledger, optimize waste disposal and transportation plan through statistical law | ||
Starting from the purpose of “Promote construction through evaluation,” the above 3 schemes and 4 Level variables should be set as an evaluation index, and the corresponding promotion strategy can be refined into secondary indicators, which can enrich the existing index system to a “source—process—result” indicators cover the whole process and make a comprehensive evaluation of GRE.
6. Conclusions
Lack of attention to dynamic process in the engineering practice is a problem in existing green evaluation index system, which caused a research interests in change mechanisms of GDR and constructed the GRE dynamics model to make clear the 3 sources and 2 promotion paths of GDR, in order to put forward targeted strategy to GDR promotion from classification management idea. The main contents and significance include the following:
(1) Through the definition of the concept of GDR, we clearly defined the measuring method of relative value (control value, actual value) in the whole process for the green degree. Although the GDR index has the possibility of imperfection, the main significance is to break the limitation of a static description of green degree by the absolute final value in the past;
(2) Simplify and deconstruct the GRE system structure based on the causality of “input-output,” clarify the primary and secondary objectives of engineering practice through the cognition of the relationship between various parts, and further focus on engineering practice system to determine the research boundary range of GDR, to put forward the necessity of dynamic improvement research for GDR;
(3) Based on the boundary and object analysis of GRE, establish the overall system causality diagram firstly according to the principle of construction procedure, then focus on 4 aspects including ecological damage, environmental pollution, land occupation, and resources consumption to establish causality diagram severally. According to the characteristics and the causal relationship between the factors, the parameter classification and equation were designed. Thus, the dynamic flow diagram of the GRE system is formed to clarify the source and optimization path of GDR.
There are still some deficiencies in this study, and the key problem is that there is no further verification of the system dynamics model. However, the purpose of this paper is to analyze the dynamic relationship between the GDR index of railway engineering and its influencing factors, which is a reasonable abstraction based on reality, and model verification is the prerequisite of simulation. Therefore, the core of this study is to construct the system dynamics flow diagram and propose the strategy for improving the GDR through the interpretation of the flow diagram, which not only puts forward the data support requirements of GDR management but also puts forward the improvement direction for the precise governance and intelligent improvement of green goals. In the future, based on the system dynamics flow diagram constructed in this paper, further quantitative research on the GDR will be carried out. Through model verification, optimization, and simulation, the change trend of the 4 status of green observation objects will be grasped so as to formulate targeted intervention control strategies, implement expected management, and improve engineering management benefits.
Acknowledgments
This work was supported by the National Natural Science Foundation of China (nos. 71942006 and 71841028) and the China Railway Group Limited (no. 2021-ZD-06).
[1] Z. Fu, Y. Sun, M. Weng, H. He, Strategic Studies on Transportation Power, 2019.
[2] J. A. Pritchard, J. Preston, "Understanding the contribution of tunnels to the overall energy consumption of and carbon emissions from a railway," Transportation Research Part D: Transport and Environment, vol. 65, pp. 551-563, DOI: 10.1016/j.trd.2018.09.010, 2018.
[3] H. Fu, H. Zhu, P. Xue, X. Hu, X. Guo, B. Liu, "Eye-tracking study of public acceptance of 5G base stations in the context of the COVID-19 Pandemic," Engineering, Construction and Architectural Management,DOI: 10.1108/ECAM-10-2021-0946, 2022.
[4] P. Gong, "Environmental impact assessment of railway construction projects based on new business types and new requirements," Railway Energy Conservation, Environmental Protection and Safety and Health, vol. 10 no. 2, 2020.
[5] D. Wang, P. Qiu, Y. Fang, "Scale effect of Li-Xiang railway construction impact on landscape pattern and its ecological risk," Chinese Journal of Applied Ecology, vol. 26 no. 8, pp. 2493-2503, 2015.
[6] Y. Sun, Research on the Major Role of Beijing-Shanghai High-Speed Railway in Economic and Social Development, 2021.
[7] X. Sun, J. Tang, M. Wang, "Study on engineering performance of green porous sponge ecological concrete," Advances in Materials Science and Engineering, vol. 2021,DOI: 10.1155/2021/8269053, 2021.
[8] X. Tang, M. Wang, Q. Wang, J. Guo, J. Zhang, "Benefits of terrestrial laser scanning for construction QA/QC: a time and cost analysis," Journal of Management in Engineering, vol. 38 no. 2,DOI: 10.1061/(asce)me.1943-5479.0001012, 2022.
[9] Compilation Committee of Qinghai-Tibet Railway, Qinghai-tibet Railway Science and Technology Volume Environmental Protection, 2016.
[10] L. Zhao, J. Mbachu, Z. Liu, "Identifying significant cost-influencing factors for sustainable development in construction industry using structural equation modelling," Mathematical Problems in Engineering, vol. 2020,DOI: 10.1155/2020/4810136, 2020.
[11] X. Tang, M. Wang, Q. Wang, J. Zhang, H. Li, J. Tang, "Exploring technical decision-making risks in construction megaprojects using grounded theory and system dynamics," Computational Intelligence and Neuroscience, vol. 2022,DOI: 10.1155/2022/9598781, 2022.
[12] H. Liu, S. Chen, "Comprehensive evaluation model and method system of product greenness," China Mechanical Engineering, vol. 9, pp. 62-65, 2000.
[13] C. Zhu, J. Shen, G. Jia, D. Wang, Q. Yin, "Fuzzy comprehensive evaluation of green degree of green building based on improved entropy weight method," Journal of Xi’an Shiyou University (Social Science Edition), vol. 30 no. 6, pp. 46-51, 2021.
[14] Y. Yang, Study on Evaluation of Greenness of Rural Roads in Cold and Arid Areas, 2021.
[15] C. Nian, Research on Measurement Method of Greenness of Prefabricated Building Construction, 2020.
[16] X. Bao, Y. Li, "Research on the green degree evaluation of machine-made sand concrete of railway in hard and dangerous mountain area," Journal of Railway Engineering, vol. 38 no. 9, pp. 81-86+105, 2021.
[17] X. Ren, Evaluation and Application of Green Degree of Temporary Facilities in Construction Site, 2021.
[18] Z. Z. Wu, K. J. Yang, X. F. Lai, M. F. Antwi-Afari, "A scientometric review of system dynamics applications in construction management research," Sustainability, vol. 12 no. 18,DOI: 10.3390/su12187474, 2020.
[19] X. N. Zhu, Y. N. Huang, R. Yan, "System dynamics-based reduction mechanism study of construction waste," Journal of Environmental Protection and Ecology, vol. 22 no. 6, pp. 2391-2401, 2021.
[20] X. Zeng, N. Huang, Y. Han, Y. Yin, J. Huang, "System dynamics analysis of construction safety risk considering existing railway lines," Computational Intelligence and Neuroscience, vol. 2022,DOI: 10.1155/2022/1256975, 2022.
[21] G. Ozcan-Deniz, Y. M. Zhu, "A system dynamics model for construction method selection with sustainability considerations," Journal of Cleaner Production, vol. 121, pp. 33-44, DOI: 10.1016/j.jclepro.2016.01.089, 2016.
[22] X. Fan, F. Zhang, Economics of Environment and Natural Resources, 2015.
[23] Y. Wu, X. Kong, Circular Economy Knowledge Reader, 2011.
[24] Alessandro, "Flora of railway environments. the San donato railway yard in Bologna," Quaderni del Museo Civico di Storia Naturale di Ferrara, vol. 6, pp. 37-44, 2018.
[25] P. Zhang, "Application of comprehensive development concept to guide the permanent-temporary combination design of railway," Journal of Railway Engineering Society, vol. 38 no. 8, 2021.
[26] Y. Liang, W. Song, X. F. Dong, "Evaluating the space use of large railway hub station areas in Beijing toward integrated station-city development," Land, vol. 10 no. 11,DOI: 10.3390/land10111267, 2021.
[27] L. I. Huajian, F. Huang, Z. Wang, L. Xun, Z. Yuan, Z. Yi, Y. Xie, "Review of material technology used in green railway tunnel engineering," Tunnel Construction, vol. 41 no. 11, pp. 1992-2000, 2021.
[28] Z. Z. Wu, A. T. W. Yu, C. S. Poon, "An off-site snapshot methodology for estimating building construction waste composition—a case study of Hong Kong," Environmental Impact Assessment Review, vol. 77, pp. 128-135, DOI: 10.1016/j.eiar.2019.03.006, 2019.
[29] J. Tang, J. Wu, M. Wang, H. Chen, B. Liu, "System review and index exploration of evaluation research of green railway engineering," Journal of Railway Engineering, vol. 38 no. 9, pp. 74-80, 2021.
[30] Q. Ye, X. Y. Bao, Q. C. Wang, "Evaluation of railway green construction scheme based on interval number attribute connection degree," Proceedings of the 2017 2nd International Conference on Civil, Transportation and Environmental Engineering (ICCTE 2017), .
[31] J. Cui, G. Ma, J. Xing, Q. Zhang, Green Design and Technology of Beijing-Zhangjiakou High-Speed Railway, 2021.
[32] H. Li, X. Bao, Journal of Railway Science and Engineering, vol. 18 no. 2, pp. 524-532, 2021.
[33] J. Xiao, H. Wang, M. Mao, "Discussion on core stakeholders of railway construction project and their function," Railway Investigation and Surveying, vol. 44 no. 2, pp. 111-114, 2018.
[34] H. Li, S. T. Ng, M. Skitmore, "Stakeholder impact analysis during post-occupancy evaluation of green buildings—a Chinese context," Building and Environment, vol. 128, pp. 89-95, DOI: 10.1016/j.buildenv.2017.11.014, 2018.
[35] B. Cheng, X. Luo, X. Mei, H. Chen, J. Huang, "A systematic review of eye-tracking studies of construction safety," Frontiers in Neuroscience, vol. 16,DOI: 10.3389/fnins.2022.891725, 2022.
[36] H. Fu, J. Niu, Z. Wu, P. Xue, M. Sun, H. Zhu, B. Cheng, "Influencing factors of stereotypes on wastewater treatment plants-case study of 9 wastewater treatment plants in Xi’an," Environmental Management, vol. 112, 2022.
[37] X. Liu, S. Chen, X. Guo, H. Fu, "Can social norms promote recycled water use on campus? the evidence from event-related potentials," Frontiers in Psychology, vol. 13,DOI: 10.3389/fpsyg.2022.818292, 2022.
[38] C. Hou, Y. Wen, Y. He, X. Liu, M. Wang, Z. Zhang, H. Fu, "Public stereotypes of recycled water end uses with different human contact: evidence from event-related potential (ERP)," Resources, Conservation and Recycling, vol. 168,DOI: 10.1016/j.resconrec.2021.105464, 2021.
[39] Y. Peng, Y. Lin, C. Fan, Q. Xu, D. Xu, S. Yi, H. Zhang, K. Wang, "Passenger overall comfort in high-speed railway environments based on EEG: assessment and degradation mechanism," Building and Environment, vol. 210,DOI: 10.1016/j.buildenv.2021.108711, 2022.
[40] C. Fan, Y. Peng, S. Peng, H. Zhang, Y. Wu, S. Kwong, "Detection of train driver fatigue and distraction based on forehead EEG: a time-series ensemble learning method," IEEE Transactions on Intelligent Transportation Systems,DOI: 10.1109/TITS.2021.3125737, 2021.
[41] B. Cheng, C. Fan, H. Fu, J. Huang, H. Chen, X. Luo, "Measuring and computing cognitive statuses of construction workers based on electroencephalogram: a critical review," IEEE Transactions on Computational Social Systems,DOI: 10.1109/TCSS.2022.3158585, 2022.
You have requested "on-the-fly" machine translation of selected content from our databases. This functionality is provided solely for your convenience and is in no way intended to replace human translation. Show full disclaimer
Neither ProQuest nor its licensors make any representations or warranties with respect to the translations. The translations are automatically generated "AS IS" and "AS AVAILABLE" and are not retained in our systems. PROQUEST AND ITS LICENSORS SPECIFICALLY DISCLAIM ANY AND ALL EXPRESS OR IMPLIED WARRANTIES, INCLUDING WITHOUT LIMITATION, ANY WARRANTIES FOR AVAILABILITY, ACCURACY, TIMELINESS, COMPLETENESS, NON-INFRINGMENT, MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE. Your use of the translations is subject to all use restrictions contained in your Electronic Products License Agreement and by using the translation functionality you agree to forgo any and all claims against ProQuest or its licensors for your use of the translation functionality and any output derived there from. Hide full disclaimer
Copyright © 2022 Juanjuan Tang et al. This is an open access article distributed under the Creative Commons Attribution License (the “License”), which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. Notwithstanding the ProQuest Terms and Conditions, you may use this content in accordance with the terms of the License. https://creativecommons.org/licenses/by/4.0/
Abstract
This article made a system dynamics flow diagram (SD flow diagram) to describe the green railway engineering (GRE) system, which provides a theoretical basis for discussing the source and change process of the green degree of railway engineering(GDR) and also provides a practical basis for accurate policy implementation and evaluation promotion of GRE management. Based on the definition of GDR and using “input-output” relationship to analyze system structure of GRE, set two green goals of environmental and resource cost decreases as the clue, deconstructed practice process based on the principle of construction to form GRE system dynamic flow diagram, which aims to reveal the key influencing factors and promotion path of GDR. The results of the research show that (1) the green schemes set the foundation of GDR, including 3 schemes of green planning, green design, green construction, and determine the expected control values (VE) of 4 status, namely ecological damage degree, environmental pollution degree, land occupation degree, and resources consume degree. (2) The deviation of expected control values (VE) and actual control values (VA) from 4 status is the premise of whether the GDR needs to be optimized or improved, and 2 practice achievements of green knowledge innovation and green culture creation provided different promotion paths for GDR. (3) According to the SD flow diagram constructed by research, the 3 schemes are influenced by regional ecological carrying capacity, social material resource reserve, green knowledge reserve, green talent reserve , reasonable goals setting, strengthening preliminary research, making full use of resources, deepening the connection of procedures, and so on are conducive to build a foundation for GDR. (4) The 4 status are directly controlled by seven rate variables, which promote the dynamic optimization of GDR by technology, equipment, institution management, and behavior management. The SD flow diagram of GRE provides 2 contributions. The first provides an analytical basis for the study of the promotion strategy of GDR, and the second provides a model basis for further quantitative study of GDR.
You have requested "on-the-fly" machine translation of selected content from our databases. This functionality is provided solely for your convenience and is in no way intended to replace human translation. Show full disclaimer
Neither ProQuest nor its licensors make any representations or warranties with respect to the translations. The translations are automatically generated "AS IS" and "AS AVAILABLE" and are not retained in our systems. PROQUEST AND ITS LICENSORS SPECIFICALLY DISCLAIM ANY AND ALL EXPRESS OR IMPLIED WARRANTIES, INCLUDING WITHOUT LIMITATION, ANY WARRANTIES FOR AVAILABILITY, ACCURACY, TIMELINESS, COMPLETENESS, NON-INFRINGMENT, MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE. Your use of the translations is subject to all use restrictions contained in your Electronic Products License Agreement and by using the translation functionality you agree to forgo any and all claims against ProQuest or its licensors for your use of the translation functionality and any output derived there from. Hide full disclaimer
Details
1 Department of Engineering Management, School of Civil Engineering, Central South University, Changsha 410075, China