Issue Title: Multidisciplinary International Scheduling Conference: Theory and Applications (MISTA) 2013-Part 2

The purpose of this research is to develop a new procedure for generating a proactive baseline schedule for the resource-constrained project scheduling problem. The main advantage of this new procedure is that it is completely independent of the reactive policy applied. This contrasts with the traditional methods that assume a predefined reactive policy. First, we define a new robustness measure, then we introduce a branch-and-cut method for solving a sample average approximation of our original problem. In a computational experiment, we show that our procedure outperforms two other published methods, assuming different robustness measures.

Details

Title
A purely proactive scheduling procedure for the resource-constrained project scheduling problem with stochastic activity durations
Author
Lamas, Patricio; Demeulemeester, Erik
Pages
409-428
Publication year
2016
Publication date
Aug 2016
Publisher
Springer Nature B.V.
ISSN
10946136
e-ISSN
10991425
Source type
Scholarly Journal
Language of publication
English
ProQuest document ID
1802626852
Copyright
Springer Science+Business Media New York 2016