This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
1. Introduction
The core of goaf retention technology is to make the basic roof above the goaf collapse along the filling body beside the goaf in time, avoiding the formation of cantilever beam structure [1–3]. In existing studies, the timely caving technology of the basic roof has been basically matured. However, in high-gas mines, the traditional roadway side filling body cannot guarantee sufficient strength to maintain the stability of the roadway and appropriate expansion to seal the goaf under pressure [4–7]. Therefore, how to realize the basic roof caving and at the same time to quickly close the goaf-retaining technology has yet to be studied.
Many scholars have carried out a large number of studies on the filling method of filling body beside goaf retaining roadway. Bai Jianbiao proposed the construction method of high-water material [8–11]. He et al. proposed the filling method of coal gangue paste material [12]. Zhang proposed the closed die casting masonry filling method [13]. Ma et al. proposed the filling method of fly ash-based cemented material [14]. Chen et al. established a mechanical model of reinforcing the filling body beside the roadway with reinforcement net and pulling anchor bolt in view of the insufficient strength of the filling body beside the roadway with high-water material, and studied and analyzed the reinforcement mechanism of reinforcing the filling body with reinforcement net and pulling anchor bolt in different deformation states [15]. Meng proposed the surrounding rock control technology, which was composed of the active support technology of high-prestressed bolt cable in roadway and the passive support technology of early-strength and collapsible roadway side filling body [16].
According to previous studies, the filling body beside the roadway should not only have sufficient support strength but also have a certain amount of shrinkage [17–20] so as to achieve the purpose of maintaining roadway stability and closed goaf. Based on the engineering technology background of 2603 working face of Zhangcun Coal Mine, Lu ’an Group, this paper puts forward the gob-side retaining technology of filling body suitable for high gas mine.
2. Engineering Geological Conditions
2.1. Occurrence Conditions and Lithologic Characteristics of Coal Seams
The 2603 working face of Zhangcun Coal Mine is located in no. 3 coal seam, with an average thickness of 4.93 m and an average dip angle of 4°. The coal seam structure is relatively simple. The average thickness of immediate roof is 3.65 m. The average thickness of the basic roof is 12.4 m. The average thickness of direct bottom is 5.7 m. The average thickness of the base is 1.85 m. According to the gas geological map and measured gas content, the total gas content is 8.2 m3/t–11.2 m3/t. The lithologic histogram of roof and floor is shown in Figure 1, and the mechanical parameters of coal and rock in roadway are shown in Table 1.
[figure(s) omitted; refer to PDF]
Table 1
Mechanical parameters of coal and rock in transport and roadway.
Lithology | H/(m) | σc/(MPa) | σt/(MPa) | σS/(MPa) | λ | E/(GPa) | φ/(°) | ρ/(kg/m3) |
Poststone | 7.83 | 55.4 | 5.3 | 12.6 | 0.25 | 45.0 | 45 | 2600 |
Mudstone | 2.49 | 28.0 | 1.7 | 5.6 | 0.28 | 11.6 | 25 | 2500 |
3# coal | 6.53 | 21.0 | 2.0 | 1.4 | 0.13 | 14.7 | 17 | 1250 |
Sandy mudstone | 2.83 | 28.0 | 2.7 | 7.0 | 0.28 | 15.5 | 23 | 2500 |
Poststone | 5.04 | 62.4 | 5.6 | 14.0 | 0.25 | 48.0 | 40 | 2700 |
2.2. Roadway Layout
3# coal seam is the last main mining seam of Zhangcun Mine. In the tunneling process, with the continuous increase of mining depth, the gas content of # 3 coal seam shows an increasing trend. To relieve the tension of mining and replace and solve the problems of gas concentration exceeding limit in the working face, the “combination” filling wall is adopted to keep the roadway in the 2603 working face. The roadway layout of 2603 working face is shown in Figure 2.
[figure(s) omitted; refer to PDF]
The mechanical model of interaction between roadway filling body and roof is shown in Figure 3. The section is made at the position of the middle broken line of the slab.
[figure(s) omitted; refer to PDF]
Where q is the weight per unit length of AC block, kg/m; q0- is the unit length weight of direct roof, kg/m; M0 is the residual bending moment of A terminal, N·m; X0 is the distance between basic roof breaking line and coal wall, m; X0 is the side abutment pressure per unit length, Nm, NA is the side coal side supporting force, N; Nb is the backfill supporting force, N; NC is the side shear stress of roof goaf, MPa; a is the width of lane retention, m; d is the width of roadway side filling body, m; Pq is the support resistance of roadway side filling body, MN/m; e is the span of basic roof breakage in goaf, m; ML is the ultimate bending moment of the basic roof rock N·m; TB is the thrust of the basic roof on both sides along the break line, MPa.
The above model is simplified as follows:
(1) For bearing the pressure of the basic roof strata, the support resistance generated by the active support technology of bolt and cable in the roadway is far less than that of the filling body beside the roadway. Therefore, the influence of the support resistance in the roadway is ignored when the mechanical model of goaf retaining is established.
(2) The shear force between layers of overlying strata in goaf retaining roadway is zero, and there is no interlayer slip phenomenon
(3) The weight of the overlying strata of the basic roof is regarded as evenly distributed on the basic roof strata
(4) Bending subsidence and fracture subsidence occur on the goaf side of the basic roof with the side edge line of goaf of the filling body beside the roadway as the rotating axis
(5) Before the roof strata are cut off by the filling body beside the roadway, the supporting force of caving gangue in goaf on the basic top block AC is zero, and the vertical shear stress on the goaf side is the horizontal thrust along the rock strata direction. The calculation formula is shown as follows:
The width of the filling wall can be calculated by establishing the mechanical equations of AB and BC rock blocks with the balance method.
BC block, perpendicular to inclination α,
Parallel to the direction,
AB block
The calculated top-cutting resistance is 19.86 MN/m. When the width of backfill is 1.5 m, the strength connecting the backfill to the top layer is no less than 14 MPa, which can meet this requirement.
3. Stability Analysis of Retaining Wall Rock under Different Parameters of “Combined” Filling Body
3.1. Influence of Different Strength of “Composite” Wall on Stability of Surrounding Rock
According to the geological conditions of the field survey, a numerical calculation model was established on the basis of FLAC3D in a length of 200 m, a width of 100 m, and a height of 100 m. The vertical direction was divided into seven layers according to the distribution state of rock strata. The bottom plate was 30 m away from the bottom boundary of the model. In the model, the upper material of the “combined” filling body near the roadway is high-water material to increase the compressive characteristics of the filling body, and the lower material is concrete material to ensure the overall strength of the filling body. In the model, the Mohr–Coulomb model is adopted for coal seam, rock stratum, and filling body near the roadway. Mechanical properties of coal strata are shown in Table 1. Mechanical properties of concrete materials and high-water materials are shown in Table 2.
Table 2
Mechanical properties of concrete materials and high-water materials.
Lithology | σc/(MPa) | σt/(MPa) | σS/(MPa) | E/(GPa) | φ/(°) | c/(MPa) |
Poststone | 39 | 4 | 6.8 | 32.5 | 55 | 12 |
Mudstone | 15.8 | 1.7 | 2.2 | 11.6 | 25 | 2.5 |
As the support layer of the “combined” backfill, the concrete material plays a decisive factor in the strength of the backfill. As the top layer of the “combined” backfill, the high-water material bears the compressible deformation characteristics of the backfill. Therefore, to investigate the influence of backfill strength on surrounding rock stability, numerical simulation was carried out on the surrounding rock stability at different strengths of 20, 30, 40, and 50 MPa supporting layers of “combined” backfill near the roadway, and the displacement variation of surrounding rock at 10 m behind the working face at 100 m was analyzed. The displacement of surrounding rock of roadway under different strength conditions of “combined” wall support layer is shown in Figure 4.
[figure(s) omitted; refer to PDF]
3.2. Influence of “Combined” Wall on Stability of Surrounding Rock
The stability of surrounding rock under the different widths of 1.2, 1.5, 1.8, and 2.1 m of the “combined” filling body at the side of the roadway was numerically simulated, and the displacement variation of surrounding rock at 10 m behind the working face at 100 m was analyzed. The displacement of surrounding rock of roadway under different widths of “combined” walls is shown in Figure 5.
[figure(s) omitted; refer to PDF]
3.3. Influence of Different Layered Heights of “Composite” Wall on Stability of Surrounding Rock
Numerical simulation was conducted on the stability of surrounding rock under the conditions of 300, 400, 500, and 600 mm heights of the top layer of “combined” backfill body, respectively, and the displacement variation of surrounding rock at 10 m behind the working face at 100 m was analyzed. Figure 6 demonstrates the surrounding rock displacement that the upper layer is invarious heights.
[figure(s) omitted; refer to PDF]
3.4. Analysis of Numerical Simulation Results
It is clearly observated that when the strength of the “composite” wall support layer is 40 MPa, the decreasing trend of top and bottom displacement slows down significantly. At this time, the top and bottom displacement is 188 mm, the two sides displacement is 28 mm, and the transverse deformation of the filling body is 3 mm. When the wall width is 1.5 m, the growth rate of roof and floor displacement slows down significantly and tends to be horizontal. Then, the roof and floor displacement is 101 mm, the two sides displacement is 22 mm, and the transverse deformation of filling body is −2 mm. When the top height of the “composite” wall is 400 mm, the displacement of the top, bottom, and two sides is the turning point, which is the minimum 252 mm, and the displacement of two sides is 41 mm. Then, the strength of the top after letting pressure is coupled with the strength of the roof rotation and subsidence process. From the three influencing factors of the strength of the support layer, the height of the top layer and the width of the filling body, the width of the filling body has the greatest influence on the “composite” wall. The displacement values of surrounding rock and filling body under three different influencing factors of “combination” support layer strength, wall width, and top layer height are shown in Figure 7.
[figure(s) omitted; refer to PDF]
4. Field Industrial Test
The maximum displacement of the top and bottom panels monitored on-site is 480 mm, and the maximum displacement of the two sides is 122 mm, both located at the end bracket. The average displacement of the top and bottom panels is 208 mm, and the average displacement of the two sides is 56 mm. The gas concentration reaches a maximum of 0.253% in the upper corner of the return air and then shows a downward trend until 0.132%. As can be seen from the effect of roadway retention and gas concentration, the “combined” filling wall has a significant effect on roadway retention along goaf. The change value of roof and floor displacement in the top roadway monitored on-site is shown in Figure 8(a), and the change value of gas concentration is shown in Figure 8(b).
[figure(s) omitted; refer to PDF]
5. Conclusion
In this article, a novel gob-retaining technology of the “combined” filling body (GRT-CFB) at the side of the roadway was proposed. To verify the superiority of novel technology, a GTR-CFB was constructed at 2603 longwall panel in Zhangcun coal mines. Based on the mechanical model, FLAC3D was used to determine the optimum parameters of filling wall “combination.” The following conclusions are drawn:
(1) The traditional concrete filling wall and high-water material filling wall cannot achieve the goal of effective control of the surrounding rock and the airtight goaf; therefore, high gas coal mine is put forward in the “combination” on the wall filling way to pick the top above that can achieve rapid airtight mined-out area, below the support layer provides the main support for the wall, to ensure the stability of roadway surrounding rock and filling body.
(2) In the field practices, the lower 3300 mm of the “combined” filling wall is constructed with C40 concrete as the supporting layer, and the upper layer is constructed with 1.2 : 1 high-water material as the connecting top layer, making full use of the pressure-shrinkable characteristics of high-water material and the high-strength characteristics of concrete. Based on the field data, the newly proposed GRT-CFB can effectively support the upper stratum and isolate the waste gas in the gob.
Acknowledgments
The authors gratefully acknowledgement financial support provided by the Key projects of the Joint Fund of the National Natural Science Foundation of China (U21A20107), the Independent research Project of State Key Laboratory of Coal Resources and Safe Mining, and CUMT (SKLCRSM001).
[1] J. Y. Chen, "Research on collaborative control technology of surrounding rock pressure relief support along goaf retaining roadway," Coal Science and Technology, vol. 48 no. 8, pp. 44-49, 2020.
[2] M. H. Dong, B. Z. Yang, H. Z. Zhou, "Research on coal pillar-free mining technology of goaf caving roadway," Coal Technology, vol. 38 no. 9, pp. 34-37, 2019.
[3] L. Ji, S. P. Wang, Y. Q. Liu, "Discussion on surrounding rock support technology of goaf retaining under secondary mining," Coal Technology, vol. 39 no. 9, pp. 15-17, 2020.
[4] N. Zhang, C. L. Han, J. G. Kan, X. G. Zheng, "Theory and practice of surrounding rock control along goaf retaining roadway," Journal of China Coal Society, vol. 39 no. 8, pp. 1635-1641, 2014.
[5] J. Yang, M. C. He, C. Chen, "Design principles and key technologies of gob side entry retaining by roof pre-fracturing," Tunnelling and Underground Space Technology Incorporating Trenchless Technology Research, vol. 90 no. 7, pp. 51-63, DOI: 10.1016/j.tust.2019.05.013, 2019.
[6] J. Wu, Y. Dong, Y. Jiang, Y. Yang, H. Sun, D. Yin, W. Gu, G. C. Zhang, "Research on plastic zone evolution law of surrounding rock of gob-side entry retaining under typical roof conditions in deep mine," Shock and Vibration, vol. 2020,DOI: 10.1155/2020/8864991, 2020.
[7] J. Yang, H. Y. Wang, Y. J. Wang, Y. B. Gao, J. W. Wang, Journal of Mining and Safety Engineering, vol. 36 no. 6, pp. 1137-1144, 2019.
[8] J. B. Bo, C. J. Hou, C. G. Zhang, T. M. Yang, D. G. Zhang, H. W. Niu, "Industrial test of filling roadway with high water Material," Coal Science and Technology, vol. 10, pp. 30-31 + 9, 2000.
[9] H. P. Jia, "Application of high water filling material in goaf retaining roadway in Tongchang Mine," Energy and Energy Conservation, vol. 11, pp. 155-156+184, 2020.
[10] X. F. Li, Z. Q. Xiong, P. Wang, China Safety Science Journal, vol. 30 no. 5, pp. 95-100, 2020.
[11] X. F. Li, Z. Q. Xiong, Y. H. Zhang, C. D. Su, Journal of Chongqing University, vol. 43 no. 4, pp. 94-106, 2020.
[12] R. J. He, H. Q. Zhou, B. C. Zhang, Energy Technology and Management, vol. 4, pp. 51-53, 2006.
[13] L. N. Zhang, Material optimization design and performance research of closed die casting goaf retaining wall, 2012.
[14] L. Ma, F. Y. Li, W. B. Nie, Mining Engineering Research, vol. 29 no. 2, pp. 42-45, 2014.
[15] Y. Chen, J. B. Bo, X. Y. Wang, S. Q. Ma, Y. Xu, T. F. Bi, H. Q. Yang, Journal of China Coal Society, vol. 37 no. 6, pp. 903-910, 2012.
[16] Q. A. Meng, "Surrounding rock control mechanism and engineering application of gob-side entry retention in high gas face," Coal Mine Safety, vol. 50 no. 02, pp. 165-168+172, 2019.
[17] G. X. Ye, Q. J. Zhu, S. X. Li, Z. X. Yu, Journal of Mining and Safety Engineering, vol. 33 no. 5, pp. 787-794, 2016.
[18] D. S. Zhang, X. X. Miao, G. M. Feng, Z. Q. Song, Journal of China University of Mining & Technology, vol. 3, pp. 23-26, 2003.
[19] S. Y. Chen, M. C. He, H. J. Wang, G. X. Yuan, F. Zhao, Journal of Mining and Safety Engineering, vol. 36 no. 04, pp. 660-669, 2019.
[20] Science-Materials Science and Engineering, "Researchers from Xi’an university of science and technology detail findings in materials science and engineering (Gob-side entry retaining technology with advanced empty hole butterfly-shaped weakening in three-soft coal seam in China)," Journal of Engineering, vol. 2020, 2020.
You have requested "on-the-fly" machine translation of selected content from our databases. This functionality is provided solely for your convenience and is in no way intended to replace human translation. Show full disclaimer
Neither ProQuest nor its licensors make any representations or warranties with respect to the translations. The translations are automatically generated "AS IS" and "AS AVAILABLE" and are not retained in our systems. PROQUEST AND ITS LICENSORS SPECIFICALLY DISCLAIM ANY AND ALL EXPRESS OR IMPLIED WARRANTIES, INCLUDING WITHOUT LIMITATION, ANY WARRANTIES FOR AVAILABILITY, ACCURACY, TIMELINESS, COMPLETENESS, NON-INFRINGMENT, MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE. Your use of the translations is subject to all use restrictions contained in your Electronic Products License Agreement and by using the translation functionality you agree to forgo any and all claims against ProQuest or its licensors for your use of the translation functionality and any output derived there from. Hide full disclaimer
Copyright © 2022 Ning Huang et al. This is an open access article distributed under the Creative Commons Attribution License (the “License”), which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. Notwithstanding the ProQuest Terms and Conditions, you may use this content in accordance with the terms of the License. https://creativecommons.org/licenses/by/4.0/
Abstract
In high gas mines, the safety accidents of coal seam spontaneous combustion and gas leakage in goaf caused by fresh air flow entering goaf due to loose roof connection of filling body beside goaf are easy to occur. In order to solve such problems, this paper proposes the gob-retaining technology of the “combined” filling body at the side of the roadway. The upper layer of the “combined” filling body is constructed with high-water material as the “connecting top layer” so that the deformation form of the filling body is consistent with the broken characteristics of the roof, and the lower layer is constructed with concrete as the “supporting layer” to achieve sufficient support strength. The “combined” filling body can not only ensure the stability of roadway surrounding rock but also a timely closed goaf. The gob-retaining technology of the “combined” filling body was applied in the field of coal mine 2603 working face. Based on the engineering background, the mechanical model was established to calculate cutting resistance of the filling body, and Flac3D software was utilized to optimum parameters of the “combined” filling body. According to the field monitoring results, the “combined” filling wall at the side of the roadway effectively controls the stability of surrounding rock and the gas concentration in the roadway.
You have requested "on-the-fly" machine translation of selected content from our databases. This functionality is provided solely for your convenience and is in no way intended to replace human translation. Show full disclaimer
Neither ProQuest nor its licensors make any representations or warranties with respect to the translations. The translations are automatically generated "AS IS" and "AS AVAILABLE" and are not retained in our systems. PROQUEST AND ITS LICENSORS SPECIFICALLY DISCLAIM ANY AND ALL EXPRESS OR IMPLIED WARRANTIES, INCLUDING WITHOUT LIMITATION, ANY WARRANTIES FOR AVAILABILITY, ACCURACY, TIMELINESS, COMPLETENESS, NON-INFRINGMENT, MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE. Your use of the translations is subject to all use restrictions contained in your Electronic Products License Agreement and by using the translation functionality you agree to forgo any and all claims against ProQuest or its licensors for your use of the translation functionality and any output derived there from. Hide full disclaimer
Details

1 China Construction Bureau South China Regional Co., Shenzhen, China; School of Mining Engineering, China University of Mining and Technology, Xuzhou, China
2 School of Mining Engineering, China University of Mining and Technology, Xuzhou, China
3 Shenzhen Construction Engineering Quality and Safety Supervision Station, Shenzhen, China
4 China Construction Bureau South China Regional Co., Shenzhen, China