The largest wind turbine manufactured in the United States is running into some technical difficulty.
Clipper Windpower Inc.'s 2.5-MW Liberty wind turbines at the 20-MW Steel Winds facility in Lackawanna, N.Y., are malfunctioning due to faulty gear sets.
"At first, we were receiving great performance from the turbines," said Michael Alvarez, executive vice president and COO of UPC Wind Partners LLC, which co-owns the facility with BQ Energy LLC. "Over the summer, a gear-timing issue in the drive train's secondary stage was detected in some of Clipper Windpower's Liberty wind turbines at the Steel Winds site. The cause was found to be a supplier quality deficiency in the drive train attributable to the suppliers' manufacturing process. As part of Clipper's warranty, upgraded drive trains will be installed into all eight turbines at the Steel Winds site. Currently, two turbines are in operation."
UPC Wind partnered with BQ Energy to produce and sell energy, capacity and renewable energy certificates generated by Steel Winds to energy retailer Constellation NewEnergy Inc., a subsidiary of Constellation Energy Group Inc., through 2009, Alvarez said....