Content area
Full Text
The Munitions Readiness Reporting (MRR) system is fed by many data sources. Assets and requirements are the intrinsic inputs. MRR assets are worldwide, less War Reserve Stocks for Allies, and include both serviceable and unserviceable munitions. Condemned assets are not included. Currently, production deliveries capture FY03 and prior year undelivered Army programs.
MRR requirements are war reserve and annual training. For a training-unique item, the training pipeline provides inventory incrementally to support training continuity. It is currently defined as 150 days or 41 percent of annual training requirements.
Hierarchies are built for the S, R, Q and B resource areas at the item level. For example, an S1 rating indicates enough assets are on hand to satisfy at least 90 percent...